RFP Key Dates
See details on the RFP key dates below.
RFP Key Dates:
Milestone Date:
RFP submitted to UT Public Service Commission for review: 11/19/2024
RFP issued to market and Q&A period begins: 5/22/2025
Q&A period ends: 6/10/2025
RFP bids due: 7/10/2025
Phase 1: Consultant completes bid eligibility screening and begins phase 2 evaluation: 7/25/2025
Phase 2: Agency selects Initial Short List: 9/15/2025
Phase 3: PacifiCorp begins modeling system benefits
Phase 3: PacifiCorp delivers system benefit modeling results to Agency: 12/8/2025
Phase 3: System benefit and indicative costs discussions with Agency begins: 12/22/2025
Phase 3: System benefit and indicative costs discussions with Agency ends: 1/12/2026
Phase 3: Agency completes Final Short List evaluation: 1/12/2026
Bidders notified of Final Short List selection: on or after 1/12/2026
Agency Board selects one or more project bids from Final Short List for contract negotiation: 2/2/2026
Execute agreements: 3/9/2026
File selected resource valuation with Commission for approval of program resource PPA and associated allocation of costs: 5/8/2026
Targeted hearing date (75 days): 7/22/2026
Please note that all future dates are estimates and subject to change